This doc walks through each PSS Podio app—what it does, what's in it, and how you'll use it.


1. Projects App (The Hub)​

Projects app showing a list of active projects

What It Does​

The Projects app is your central dashboard. Every job lives here. It's the starting point for everything.

Key Information Stored​

FieldPurpose
Job IDAuto-generated identifier (Job # + Job Name)
Job #Your unique number for this project
Job NameThe project name
CompanyWhich company/GC this is for
DivisionConcrete, Drywall, or Other
ScopesWhat types of work (Earthwork, Utilities, Foundations, etc.)
Current Stage StatusWhich stage is currently active
Location/AddressWhere the job site is

People Fields​

FieldRole
Project Manager (PM)Overall project ownership
OC (Operations Coordinator)Office-side coordination
FOCS (Field Operations Coordinator)Field-side coordination
ForemanOn-site crew lead
Customer / GCLinked contact record

Financial Fields​

FieldWhat It Tracks
Project BudgetExpected costs
Contract ValueWhat you're billing
VarianceBudget minus actual (calculated)

Progress Tracking​

FieldWhat It Shows
Overall ProgressAverage completion across stages (calculated)
Open Tasks CountIncomplete tasks remaining (calculated)
Linked StagesThe 5 stages for this project
Linked Safety & ComplianceSafety records for this project

How You'll Use It​

  • Starting a new job: Create a project item here first
  • Checking status: Look at Current Stage Status and Overall Progress
  • Finding everything: Use linked fields to jump to stages, tasks, contacts

2. Stages App​

Stages app list view showing all stages across projects

What It Does​

Breaks each project into 5 phases. Stages help you track progress and know what's active.

The 5 Stages​

#StageWhat Happens
1Pre-ConstructionPlanning, permitting, submittals, safety setup
2MobilizationSite setup, equipment delivery, crew assignment
3ConstructionActive work, daily reports
4DemobilizationCleanup, equipment return, punch list
5RetainageFinal billing, project closeout

Key Fields​

FieldPurpose
Stage NameWhich of the 5 stages this is
Linked ProjectThe project this stage belongs to
Estimated/Actual DatesWhen the stage should run
Tasks Complete %Progress (calculated)
Open IssuesCount of incomplete tasks (calculated)
Task OverviewAll tasks linked to this stage
Stage Specific NotesNotes for this phase
Automation StatusTracks if tasks have been auto-created

How Stages Are Created​

You don't create stages manually. When you create a project, automations create all 5 stages automatically.

How You'll Use It​

  • See what's happening: Check Tasks Complete % for progress
  • Jump to tasks: Use Task Overview to see everything in that stage
  • Review dates: Update Estimated/Actual as plans change

3. Tasks App​

Task list showing different statuses with color indicators

What It Does​

Holds every individual action item across all projects. This is where day-to-day work gets tracked.

Key Fields​

FieldPurpose
Task NameWhat needs to be done
Task #Unique number
StatusPending (red), In Progress (yellow), Complete (green)
Due DateDeadline
ResponsibleWho owns this task
TypeTask, Recurring, or Subtask
NotesAdditional details or instructions
AttachmentsUploaded files

Relationship Fields​

FieldLinks To
Linked StageWhich stage this task belongs to
Linked ProjectWhich project this task belongs to
DependenciesOther tasks that must complete first
Linked Parent TaskFor subtasks—the main task they belong to

Task Dependencies​

Some tasks can't start until others finish. These are "Dependent" tasks.

FieldMeaning
Ind or DepIndependent = can start anytime; Dependent = waits for something
DependenciesThe specific task(s) that must finish first

When a prerequisite task completes, dependent tasks automatically move to "In Progress."

Task showing Dependencies field with linked prerequisite

How Tasks Get Created​

Most tasks are auto-created when the project is created. The system copies from Task Templates and links everything correctly — all tasks for all stages are generated at once.

Some tasks you'll create manually—ad-hoc work that wasn't templated.

How You'll Use It​

  • Check your work: Filter by Responsible = You, Status ≠ Complete
  • Update progress: Change Status as you work
  • See blockers: Check Dependencies to know what you're waiting on

4. Safety & Compliance App​

Safety & Compliance detail page showing compliance types and linked tasks

What It Does​

Tracks safety-related compliance items that span multiple stages of a project.

Compliance Types​

TypeWhat It Covers
811 LocateUnderground utility location requests
BadgingSite access credentials and background checks
SSSPSite-Specific Safety Plan documentation

Key Fields​

FieldPurpose
Compliance Type811, Badging, or SSSP
NotesDetails and updates
FilesUploaded documents
Related TasksTasks linked to this compliance item
Linked ProjectWhich project this belongs to

How Safety Records Get Created​

A Safety & Compliance record is auto-created when you create a project.

How You'll Use It​

  • Track compliance status: See what's pending for a project
  • Store documents: Upload SSSP plans, 811 confirmations, badge info
  • Link to tasks: Connect compliance items to specific tasks

5. Contacts App​

Contact record showing name, company, and linked projects

What It Does​

Stores GC and customer contact information. Reusable across multiple projects.

Key Fields​

FieldPurpose
NameContact's full name
Job TitleTheir role
OrganizationWhich company they work for
EmailContact email
PhoneContact phone
AddressPhysical address
NotesAdditional info
Linked ProjectsAll projects involving this contact

How You'll Use It​

  • Find contact info: Look up who to call/email
  • Link to projects: Connect a contact to their project(s)
  • Avoid duplicates: Search before creating—they might already exist

6. Task Templates App (Utility)​

What It Does​

The master list of tasks that automations copy from. You rarely open this directly.

Key Fields​

FieldPurpose
Project StageWhich stage this template is for
Task #Template task number
TasksTask name
ResponsibleWho typically owns this (role/function)
DivisionConcrete, Drywall, or Other
Independent or DependentCan it start immediately?
Dependent Task #Which task must finish first
TypeTask, Recurring, or Automation
Linked SubtasksSubtask templates that belong to this

How Templates Work​

When a project is created, GlobiFlow automations:

  1. Find templates matching that stage + division
  2. Create actual tasks from each template
  3. Link them to the correct stage and project
  4. Create any subtasks
  5. Set up dependencies between tasks

Task Template detail page showing key fields like Responsible Role, Type, Notes, and Division


7. Subtask Templates App (Utility)​

What It Does​

Holds subtask definitions linked to main task templates. Also used by automations.

Key Fields​

FieldPurpose
Linked Main TaskWhich task template this subtask belongs to
Subtask #Number within the parent task
SubtasksSubtask name/description
NotesAdditional details
DivisionConcrete, Drywall, or Other

Summary: Which Apps You'll Use​

How OftenApps
DailyTasks, Projects
WeeklyStages, Safety & Compliance
As NeededContacts
Rarely/NeverTask Templates, Subtask Templates

The template apps are the "engine room." They power the automations, but you don't need to go there.


Related Docs: